Dongguan factory old equipment relocation
东莞搬迁1个工厂到泰国、印尼、日本3个工厂
Customer demands
1. Clean up the old production line with hazardous chemicals;
Dust protection treatment for dismantling old production lines;
Prevent the diffusion of residual chemical substances in the surrounding environment of old production lines;
Safety and security logistics after dismantling complex equipment;
Special packaging for corrosion prevention, leakage prevention, and dust dispersion prevention;
2. One production line needs to be relocated to three production lines located in different countries, and the difficulty of customs clearance for special equipment is high. There are many target locations for equipment relocation, which require separate management; Complete restoration in 3 different factories; The complex dismantling of multiple equipment requires multiple special dismantling and restoration installation technical capabilities
3. Strict schedule requirements: It is strictly required that disassembly, transportation, and installation must be completed within the specified time
Solution
Jinhe Production Line Project Delivery Solution (for relocation scenarios)
Customer revenue
1. Save installation time by 2 months
2. Zero hidden dangers within one year after production
3. Revise the limitations of the original factory building on site, quickly design and implement renovation
4. The environment and process remain unchanged to the maximum extent possible, and workers are directly employed and immediately put into production on a large scale
5. Zero safety accidents